Construction

Progress Billing for Contractors: AIA G702 and G703 Forms Explained

Written by Mubashar Hassam, CPA

Progress billing is how most commercial construction projects are invoiced β€” you bill the owner incrementally as the work progresses rather than in one lump sum at the end. The AIA G702 and G703 forms are the standard format for this in the US commercial construction industry. If you work with general contractors, developers, or public agencies, you will almost certainly need to use them.

What Is Progress Billing?

Progress billing allows a contractor to invoice a portion of the contract value as work is completed. Instead of waiting until the project is finished to get paid, you invoice monthly (or at defined milestones) for the work done that period. This is critical for cash flow on longer-duration projects β€” waiting until completion on a 12-month, $2M project to invoice would be financially devastating for most contractors.

The AIA G702: Application and Certificate for Payment

The G702 is the cover sheet for a progress billing submission. It summarises: the total original contract sum, any approved change orders (additions or deductions), the revised contract sum, work completed and stored materials to date, the amount previously billed, the current payment application amount, and the retention amount being held. The owner or their lender signs the G702 to approve payment.

The AIA G703: Schedule of Values

The G703 is the supporting schedule behind the G702. It breaks the contract down into individual line items (divisions of work), each with a scheduled value. For each period, you indicate the percentage or dollar amount of each line item completed. This transparency is what makes the format trusted by owners and lenders β€” they can see exactly what has been done and validate the billing.

How to Tie G702/G703 Billing to Your Bookkeeping

Every approved G702 billing should be entered as an invoice in your accounting system against that project. The retention amount is not cash you receive β€” record it in a Retention Receivable account separate from your regular AR. When the project is complete and retention is released, that balance transfers to AR and is collected. Failure to track retention separately is one of the most common construction bookkeeping errors.

Need expert help with this?

Our ex-Big 4 CPA team handles this for US clients remotely. Book a free 30-minute consultation.

Book a Free Call β†’

Frequently Asked Questions

What is AIA billing in construction?
AIA billing refers to the use of American Institute of Architects standard forms β€” primarily the G702 (Application and Certificate for Payment) and G703 (Schedule of Values) β€” for submitting progress payment requests on construction projects. It is the standard format required by most commercial owners, developers, and public agencies in the US.
What is the difference between the G702 and G703 forms?
The G702 is the summary cover sheet that shows total billing amounts, previous billings, the current application amount, and retention. The G703 is the detailed Schedule of Values that breaks the contract into line items and shows the percentage or dollar amount of each completed to date. The two forms are submitted together.
What is retention in construction billing?
Retention (also called retainage) is a percentage β€” typically 5–10% β€” of each progress payment that the owner withholds until the project is substantially complete. It protects the owner against incomplete work or defects. From a bookkeeping perspective, the withheld retention is a receivable that cannot be collected until project closeout.
Do I need to use AIA forms for all construction billing?
AIA forms are standard for commercial construction, particularly on projects with GCs, developers, or public agencies. Residential remodelling and smaller jobs often use simpler invoice formats. Your contract with the project owner typically specifies whether AIA billing is required.
How is percentage of completion calculated for progress billing?
The most common method is cost-to-cost: percentage complete = costs incurred to date Γ· total estimated cost at completion. If a project has a $500,000 total estimated cost and you have spent $200,000, you are 40% complete and can bill 40% of the contract value (less retention). Some contracts use a schedule of values with pre-agreed percentages per work division instead.

About the Author

Mubashar Hassam, CPA
Mubashar Hassam, CPACPA | Construction & CFO Specialist
View full profile β†’

Work With Our Team

Ex-Big 4 CPAs serving US clients remotely. Free consultation.

Book Free Call β†’
← Back to Blog